Renovation Update!

Traffic signal imageThe facade of Gelman's new entrance is taking shape! Exterior finishes like railings and the glass canopy will continue to be installed over the next two weeks. You can get an excellent view of this from Kogan Plaza. The inner perimeter rooms will be receiving their finishing touches and furniture, allowing for technology to be installed and a chance for staff to start testing in these areas.

Starting June 24th, our loading dock will be operational.  Our temporary dock will still be used for construction traffic only. On June 19th beginning at 7 p.m., there will be a crane hoist on the 22nd St side of the building.  This will close the street and sidewalk to traffic.  Please use caution when walking in this area.

 